Provision of a New Telemetry System
A Contract Award Notice
by THE COAL AUTHORITY
- Source
- OJEU
- Type
- Contract (Services)
- Duration
- 7 year (est.)
- Value
- £1M
- Sector
- INDUSTRIAL
- Published
- 26 Jan 2021
- Delivery
- To 26 Jan 2028 (est.)
- Deadline
- n/a
Concepts
Location
The Telemetry replacement project will cover 47 Mine Water Treatment Schemes (MWTS) located over 49 separate sites. These sites are located on the Coalfields in Scotland, the North East, the North West.
2 buyers
- Coal Authority Mansfield
1 supplier
- Schneider Electric Systems Telford
Description
The Coal Authority (TCA) wishes to appoint a contractor to provide a replacement telemetry system for the Mine Water Treatment Schemes (MWTS) it owns and manages. These schemes remove contaminants, such as iron, from water that flows through old mine workings, before discharging the treated water back into the watercourse. Being able to monitor the health and performance of the equipment at these schemes is therefore vital in ensuring the effective running of the schemes and in helping TCA to meet the discharge consents set by the Environment Agency. The Telemetry replacement project will cover 47 Mine Water Treatment Schemes (MWTS) located over 49 separate sites. These sites are located on the Coalfields in Scotland, the North East, the North West, Yorkshire, the Midlands and Wales, with a total of 39 sites in England, five sites in Wales and five sites in Scotland. Some of these sites are covered by an existing telemetry system, which will be replaced by the new system.
Total Quantity or Scope
The Coal Authority (TCA) wishes to appoint a Contractor to provide a replacement telemetry system for the Mine Water Treatment Schemes (MWTS) it owns and manages. These schemes remove contaminants, such as iron, from water that flows through old mine workings, before discharging the treated water back into the watercourse. Being able to monitor the health and performance of the equipment at these schemes is therefore vital in ensuring the effective running of the schemes and in helping TCA to meet the discharge consents set by the Environment Agency. The Telemetry replacement project will cover 47 Mine Water Treatment Schemes (MWTS) located over 49 separate sites. These sites are located on the Coalfields in Scotland, the North East, the North West, Yorkshire, the Midlands and Wales, with a total of 39 sites in England, five sites in Wales and five sites in Scotland. Some of these sites are covered by an existing Telemetry system, which will be replaced by the new system. The Mine Water Treatment Schemes that are in scope for the Telemetry project fall into five categories, which are listed, in the table below: Type number description number of schemes: — 1 pumped passive 33, — 2 pumped- chemical dosed 8, — 3 active process plant 1, — 4 pumping stations 5, — 5 gas fan stations 2, — 49. The following table shows the geographical distribution of schemes in each category: Area pumped passive pumped- chemical dosed active process plant pumping stations gas fan stations: Number of schemes — Scotland 2 2 0 1 0 5, — North East 9 2 1 4 2 18, — North West 7 3 0 0 0 10, — Yorkshire 5 0 0 0 0 5, — Midlands 6 0 0 0 0 6, — Wales 4 1 0 0 0 5, — Total 33 8 1 5 2 49.
Award Detail
1 | Schneider Electric Systems (Telford)
|
Award Criteria
Technical questions | 65.0 |
PRICE | 35.0 |
CPV Codes
- 51230000 - Installation services of testing equipment
- 38291000 - Telemetry apparatus
Indicators
- Award on basis of price and quality.
Reference
- OJEU 040349-2021