Essex Waste Management Partnership Residual Waste Treatment Contract

A Voluntary Ex-Ante Transparency (VEAT) Notice
by ESSEX COUNTY COUNCIL

Source
OJEU
Type
Contract (Works)
Duration
not specified
Value
£10M
Sector
CONSTRUCTION
Published
21 Mar 2022
Delivery
not specified
Deadline
n/a

Concepts

Location

Courtauld Close, off Courtauld Road, Basildon, Essex, SS13 1FL

Geochart for 2 buyers and 1 suppliers

2 buyers

1 supplier

Description

The purpose of this Notice is to inform the market of the additional works/services to be performed by UBB Waste (Essex) Limited following a proposed amendment of its contract with ECC for the design, construction, commissioning, operation and handback of a mechanical biological treatment facility in Basildon. The facility did not pass the acceptance tests specified in the contract which led to ECC commencing litigation against the contractor. The Authority has given notice that it is proposing to take a decision to enter into an Agreement to settle that litigation and to amend the handback requirements of the contract such that the site will be returned to ECC in a condition that will allow for its future redevelopment. It is expected that the modified contract will expire in 2040. These additional works/services are essential to restore the pre-contract position and form an integrated part of the proposed settlement to draw to a conclusion to the litigation between the parties.

Total Quantity or Scope

The Contract was awarded on 31 May 2012 to UBB Waste (Essex) Limited, following the completion of a full tender process. The contracted works and services were for the design, construction, commissioning, handback and operation of a mechanical biological treatment (MBT) facility in the Tovi Eco-Park (Basildon, Essex). Following the initial construction of the facility, the contract provided for a commissioning period followed by Acceptance Tests to confirm that the facility could meet the performance requirements in the contract. If not ultimately passed by an Acceptance Longstop Date of 12 January 2017, the Authority was entitled to terminate the Contract. The facility did not pass the Acceptance Test by the Acceptance Longstop Date, which resulted in the Authority commencing litigation against the contractor. The Authority has given notice that it is proposing to take a decision to enter into an Amendment and Settlement Agreement to settle that litigation and to amend the handback requirements of the contract on the basis that the site will be cleared and returned to ECC in a condition that will allow for its future redevelopment. It is expected that the modified contract will have a term expiring in 2040. More specifically, the contractor shall: - Demolish the MBT facility to ground slab level. - Surrender the Environmental Permit which relates to the operation of the MBT facility and is held by Urbaser Environmental Limited. - Remove certain hazardous substances from the site and hand back the site in accordance with the conditions in the Amendment and Settlement Agreement, to the satisfaction of an independent environmental consultant. - Remove certain plant and equipment from the MBT facility prior to its demolition. - Design and build a new surface water management system for the site. This includes re-grading part of the site and installing new surface water retention structures. - Install new sections of security fencing for the site. - Arrange for the de-energisation of the UKPN electrical sub-station and install a new power supply to the site to serve the surface water management system. - Fill below-ground voids following the demolition process with granular materials. - Obtain all necessary consents to enable the works. - Surrender to the Authority its sub-lease interest in the site. - Procure that its ultimate parent companies indemnifies the Authority (until expiry of a period of three years following handback) against any failure by the contractor to perform its obligations as set out above and further detailed in the Amendment and Settlement Agreement.

Award Detail

1 Ubb Waste Essex (Cheltenham)
  • Value: £9,900,000

CPV Codes

  • 45111000 - Demolition, site preparation and clearance work
  • 45111300 - Dismantling works
  • 45200000 - Works for complete or part construction and civil engineering work
  • 90000000 - Sewage, refuse, cleaning and environmental services

Indicators

Other Information

Following publication of this Notice, Essex County Council will allow at least a 10 day standstill period prior to entering into the contract. Linked to Original OJEU Number: 2009/S 225-323258

Reference

Domains