GB-Swindon: UKRI-2461 Sextupoles for the FEBE Arc Line

A Contract Award Notice
by UK RESEARCH & INNOVATION

Source
Contracts Finder
Type
Contract (Products)
Duration
11.5 month
Value
£53K
Sector
INDUSTRIAL
Published
27 Sep 2022
Delivery
28 Sep 2022 to 11 Sep 2023
Deadline
26 Sep 2022 00:00

Concepts

Location

Geochart for 1 buyers and 1 suppliers

1 buyer

1 supplier

Description

The Science and Technology Facilities Council (STFC) requires a pair of sextupole magnets for the Full Energy Beam Exploitation (FEBE) section of the Compact Linear Accelerator for Research Applications (CLARA), a linear accelerator currently under construction at STFC Daresbury Laboratory. The sextupoles are a recent change in design to a beamline which has already begun construction and as such are strictly limited in total length to no more than 100mm, and are expected to be used at gradients of up to 255 T/m2 for a total integrated gradient of between 24.5 and 25 T/m. These magnets will be positioned in a left-right arc section of beamline with high transverse beam dispersion and will be used to help control the linear dispersion with the aid of a beam mask, allowing us to deliver highly compressed electron beams to users. The electron beam energy through these magnets will be up to 250 MeV.

Award Detail

1 Danfysik A S (Taastrup)
  • Value: £53,200

CPV Codes

  • 31630000 - Magnets

Other Information

Procurement Contract Transparency Data: Redacted contract documents will be made available within the next 30 days on the UKRI website at: https://www.ukri.org/about-us/procurement-contract-transparency-data/ Please follow this link to view the notice https://www.delta-esourcing.com/delta/respondToList.html?noticeId=723954884