TD1922b - Assembly Rooms Principal Contractor Pre-demolition Works Option 3

A Contract Award Notice
by DERBY CITY COUNCIL

Source
Contracts Finder
Type
Contract (Works)
Duration
5.5 month
Value
£1M-£2M
Sector
CONSTRUCTION
Published
22 Mar 2023
Delivery
03 Apr 2023 to 21 Sep 2023
Deadline
01 Mar 2023 00:00

Concepts

Location

Geochart for 1 buyers and 1 suppliers

Description

Direct Award via SCAPE Construction England and Wales Up to £7.5m Procurement of a principal contractor, Morgan Sindall, to carry out pre-demolition surveys, preparing the Assembly Rooms and MSCP for demolition. Option 3 works includes: surveying RAAC planks, a demolition asbestos survey, installation of task lighting, erection of scaffolds for surveys, inspection of gantries to the Great Hall and a small element of soft strip. All the works are to be undertaken over a 20 week contract period. It is likely the Council will instruct compensation events to include other works which will increase the scope and contract value and extend the contract period by 6 to 12 months, these include: soft strip, asbestos removal, party wall negotiations and other miscellaneous surveys needed for demolition.

Award Detail

1 Morgan Sindall Construction & Infrastructure (London)
  • Value: £1,000,000

CPV Codes

  • 45100000 - Site preparation work
  • 71000000 - Architectural, construction, engineering and inspection services

Indicators

  • Contract is suitable for SMEs.

Reference

Domains