Bournemouth Pier Structural Works

A Tender Notice
by BOURNEMOUTH CHRISTCHURCH AND POOLE COUNCIL

Source
Contracts Finder
Type
Contract (Works)
Duration
21 month
Value
£8M-£9M
Sector
CONSTRUCTION
Published
07 Mar 2025
Delivery
01 Apr 2026 to 31 Dec 2027
Deadline
30 Jul 2025 13:00

Concepts

Location

Geochart for 1 buyers and 0 suppliers

Description

The structural works are to extend the life of the pier by at least 25 years. The scope includes undertaking concrete repairs, installing Impressed Current Cathodic Protection (ICCP) system and removal of timber landing stages. Due to budget constraints, the Council are considering 3 options, these being: - • Option A: All Concrete Works Only Concrete works only. No removal of any of the timber landing stages. • Option B: All Concrete Works and Part Timber Landing Stage Removal Concrete works and the complete removal of the Northern and Small Boat timber landing stages only. • Option C: All Concrete Works and All Timber Landing Stage Removal Concrete works and complete removal of all of the timber landing stages All works will be covered by a single NEC4 ECC Option A contract (incorporating a Bill of Quantities for concrete repair works). The Councils preferred option is Option C, if affordable. If this is not achievable, then the Council will consider Option B and if that isn't affordable then Option A. Suppliers can bid to any or all of the 3 options. The specifications which outline the requirements for this contract are contained with the following document 'Bournemouth Pier Structural Works - Document Schedule 16.01.2025' The successful Bidder will be expected to commence the works in May 2025 and will be required to ensure the works are completed by December 2026 (not including defects period).

CPV Codes

  • 45220000 - Engineering works and construction works
  • 45223000 - Structures construction work
  • 45223500 - Reinforced-concrete structures
  • 45241300 - Pier construction work
  • 45262330 - Concrete repair work
  • 45243300 - Sea wall construction work

Indicators

  • Contract is suitable for SMEs.

Other Information

Suppliers interested in this opportunity can access the full procurement documentation by visiting BCP Council's Tendering system www.supplyingthesouthwest.org.uk Suppliers should search for the opportunity through Supplying the South West. There are further details of the opportunity on the advert published on www.supplyingthesouthwest.org.uk and instructions on how suppliers can access the procurement documentation for completion. Responses to the opportunity must be submitted electronically through www.supplyingthesouthwest.org.uk before the deadline shown on the system. If you are unable to access the advert for the opportunity through www.supplyingthesouthwest.org.uk please contact the Council using the contact details provided. Link to Advert for Suppliers to Access Tender Documents https://procontract.due-north.com/Advert?advertId=08503e21-36d7-ef11-8133-005056...