CO Construction - LT229/230 UGC Ducts - Strathy Wood to Strathy South 0926
A Contract Award Notice
by SSE PLC
- Source
- Find a Tender
- Type
- Contract (Works)
- Duration
- not specified
- Value
- ___
- Sector
- CONSTRUCTION
- Published
- 19 May 2025
- Delivery
- not specified
- Deadline
- n/a
Concepts
Location
Caithness & Sutherland and Ross & Cromarty:
Description
The Strathy South project proposes the establishment of a 132/33kV substation to allow the connection of the Strathy South windfarm on the network. As part of these works, there is a requirement for approximately 5.5 km of new 132kV underground cable constructed from the site of Strathy South 132/33kV Substation. Due to phasing of works, there is a requirement for an advanced works package to be tendered for installation of the cable ducts. The cable ducts run under a road which will serve as the access track for the windfarm development therefore, these works will need to be completed prior to the windfarm site start date.
Total Quantity or Scope
Supply and install.
Award Detail
1 | Unnamed (None)
|
CPV Codes
- 45231400 - Construction work for electricity power lines
Other Information
** PREVIEW NOTICE, please check Find a Tender for full details. **
Reference
- ocds-h6vhtk-02874d
- FTS 022830-2025