PRO004337-Works-Contract-Haweswater Aqueduct Resilience Programme
A Utilities Contract Award Notice
by UNITED UTILITIES WATER LIMITED
- Source
- Find a Tender
- Type
- Contract (Works)
- Duration
- 33 year (est.)
- Value
- ___
- Sector
- CONSTRUCTION
- Published
- 21 Aug 2025
- Delivery
- To 29 Jun 2058 (est.)
- Deadline
- n/a
Concepts
Location
Warrington
2 buyers
- United Utilities Water Warrington
1 supplier
- Cascade Infrastructure London
Description
United Utilities Water Limited (UU) proposes to deliver a scheme titled Haweswater Aqueduct Resilience Programme (HARP DPC Project) via Ofwat’s Direct Procurement for Customers (DPC) approach, engaging a Competitively Appointed Provider (CAP) to design, build, finance and maintain this major water resilience supply project. The HARP DPC Project comprises the replacement of 6 tunnel sections of the existing Haweswater Aqueduct (HA), connections to existing multiline siphons between the tunnel sections and associated facilities. It also includes the commissioning and ongoing maintenance of those works for a period of approximately 25 years after completion.
Total Quantity or Scope
Works and services for delivering the HARP DPC Project are set out in the ‘additional information’ section. Project agreement - The CAP will be appointed under a bespoke project agreement with UU, the term of the project agreement will be 25 years, plus a construction period. Independent Technical Advisor - Assurance for UU and customers under the project agreement will be provided by an Independent Technical Advisor (ITA) and Approved Assurer (AA). The ITA and AA will be appointed through a separate procurement process. Planning - Planning submissions were made by UU for the whole of the HARP DPC Project and UU has received planning permissions from the relevant local planning authorities (subject to section 106 planning obligations). As such, UU did not remove any of the initial six tunnel sections from the scope of the HARP DPC Project during the procurement process.
Award Detail
1 | Cascade Infrastructure (London)
|
Renewal Options
The parties (UU and CAP) may agree (in their absolute discretion) to extend the project term (by up to 10% of the project term) by agreeing to amend the expiry date. Such agreement shall be in writing, and include any changes to the project agreement to account for the extension as agreed by the parties and may also be subject to Ofwat's prior approval.
Award Criteria
Technical | 60.0 |
Commercial | 40.0 |
CPV Codes
- 45000000 - Construction work
- 43123000 - Tunnelling machinery
- 43320000 - Construction equipment
- 45221000 - Construction work for bridges and tunnels, shafts and subways
- 45221200 - Construction work for tunnels, shafts and subways
- 45221240 - Construction work for tunnels
- 45221247 - Tunnelling works
- 45231300 - Construction work for water and sewage pipelines
- 45233000 - Construction, foundation and surface works for highways, roads
- 45350000 - Mechanical installations
- 50000000 - Repair and maintenance services
- 63712320 - Tunnel operation services
- 65100000 - Water distribution and related services
- 65320000 - Operation of electrical installations
- 66100000 - Banking and investment services
- 66122000 - Corporate finance and venture capital services
- 71000000 - Architectural, construction, engineering and inspection services
- 71242000 - Project and design preparation, estimation of costs
- 71322000 - Engineering design services for the construction of civil engineering works
- 71500000 - Construction-related services
- 71540000 - Construction management services
- 71541000 - Construction project management services
Indicators
- Options are available.
- Award on basis of price and quality.
Other Information
The HARP DPC Project comprises: (a) design, construction, testing and commissioning of the works; (b) planned and corrective maintenance, including lifecycle maintenance, of the assets following the completion of each section of the tunnel; (c) the project management of these activities; and (d) financing of the activities The works and services for delivering the HARP DPC Project includes (but not limited to): (a) The coordination of all design, construction, commissioning of works, implementation, and project management at all sites (b) management of limiting environmental impact to local communities (c) securing land and property rights (d) obtaining and complying with all consents (including s.106 Agreements) (e) compliance with all requirements with respect to biodiversity net gain (f) design, construction, commissioning, implementation, testing & inspection of the works (g) provision of all utilities and services necessary for the permanent operation of the new aqueduct, including activation any associated connection fees (h) surveys, monitoring, and instrumentation works and services (i) studies, investigations, and assessments (j) reinstatement of all utilities, highways, footpaths, hardstanding and other items outside of the worksite that are damaged or temporarily modified during construction of the works (k) engagement with stakeholders, local communities and third parties impacted by the HARP DPC Project (with listed exceptions) including complaints resolution (l) provision of workforce occupational health services and well-being programmes (m) ancillary activities necessary to ensure that the works and services are carried out in accordance with good industry practice (n) protection and maintenance of the works through construction, testing and commissioning periods (o) provision of as-built construction records, operation and maintenance documentation and other documentation for the HARP DPC Project (p) provision of warranties and collateral warranties for plant and materials (q) provision of temporary works to deliver the HARP DPC Project (r) undertaking acceptance tests (s) provision of all elements required for operational and maintenance access (t) securing deeds of easement and rights of access along the entire length of the new HA tunnelled sections (u) monitoring the impact of the works on private water supplies and arranging the provision of alternative water supplies where required (v) provision of all other required works, services and activities required for specified operating techniques, parameters and restraints and water quality standards.
Reference
- FTS 050621-2025